Completed phases

Completed phases

No items found.
No items found.

Over recent years several major phases of the regeneration plan have successfully been delivered. Find out more about the key projects here.

Posted:

Image credit: Ruth Houlsby

Crystal Palace Subway: 2022-2024

First opened to the public in 1865, the Subway was originally designed by Charles Barry Jnr, and provided access to the Crystal Palace from the High-Level Station. The main structure of the Subway is a series of spectacular vaults, built from red and cream brick, with an elaborate floor paved in two alternating types of stone. The Subway is one of the last remaining features of the original Crystal Palace after the 1936 fire. It has an international following and its restoration was the result of 14 years of dedicated campaigning and awareness raising  spearheaded by the Friends of Crystal Palace Subway, in collaboration with many other local stakeholders.

Thanks to £3.5m grant funding, much needed works to restore the Crystal Palace Subway were undertaken between 2022-2024. The site is partially located under Crystal Palace Parade, situated on the edge of Crystal Palace Park. The restoration of this structure will ultimately remove the Subway from Historic England’s Heritage at Risk Register, making the site safe for future generations to enjoy. The project has provided an extraordinary opportunity to secure a sustainable future for the much-loved community asset, which is of significant historical importance.

With the support of the Friends of Crystal Palace Subway and Historic England, the Council appointed award-winning conservation architects Thomas Ford & Partners in May 2020, to undertake the restoration of the Grade II* listed Subway. The project required detailed survey work to understand the current condition of the structure.

Planning approval was granted in January 2022, which included the provision of a new roof over the East Courtyard to replace the roof that was destroyed in the Crystal Palace fire of 1936.

In February 2022, specialist conservation contractors, DBR Limited, were appointed to complete the restoration works of the Subway. Subsequently, works on the Subway’s restoration began in Spring 2022 with works onsite completing in September 2024. Extensive restoration works have been undertaken, including the structural remedial works to the North Elevation, the West Courtyard gates have been installed and all masonry cleaning is complete.

In addition to the work outlined above, during the excavation of the Upper-South Stair, a half stone landing, complete with its surrounding brick walls, was uncovered. This discovery revealed that the stair had a different configuration that had been outlined on all previous historic drawings, demonstrating that the North and South stairs were not symmetrical as previously thought.

For more information about the project, please visit: www.thomasford.co.uk/crystal-palace-subway

Restoration of the outdoor Concert Platform: 2022

In 1996, Ian Ritchie Architects won a competition to design a permanent concert platform in Crystal Palace Park. The structure, which is largely made of oxidised Corten A steel, was designed on the principles of nature, gravitas, levitas and simplicity. It hosted its first concert in August 1997, and won the Civic Trust Award in 1998 as well as being shortlisted for the Stirling Prize the same year.

The area that Platform sits in, known as Crystal Palace Bowl, has a long lineage of hosted iconic musicians and performers, including Bob Marley, Elton John, and the Royal Philharmonic Orchestra, but over the years the current iteration of the stage fell into disrepair.

The campaign to 'Reboot the Rusty Laptop' was spearheaded by a local campaign group, Back the Bowl. Working in collaboration with the Trust, a Mayor of London-backed crowdfunding campaign raised over £60,000 to replace the rotten wooden stage and make a number of vital repairs that would allow the use of this iconic outdoor venue after decades of dilapidation. Additional funding was granted by The Backstage Trust and the use of income from events held in the park.

The new stage surface was installed in July 2022. Constructed with long-lasting, low-maintenance marine hardwood, it marks the end of the first phase to revive Crystal Palace Bowl and sets the stage for many more wonderful performances and activities over the coming decades. The next phase aims to modernise the backstage area and improve access to the venue.

Crystal Palace Improvement Scheme: 2015-2019

The Crystal Palace Park Improvement Scheme delivered a wide range of enhancements to the park, made possible thanks to £2.4 million of funding from the Greater London Authority, Historic England and Bromley Council. Key projects included:

  • A new café and community space
  • A new skatepark
  • Conservation of a number of the Grade I listed dinosaurs, Grade II listed sphinxes and south terrace steps
  • Installation of interpretation boards around the Tidal Lake and dinosaur island
  • Landscaping and removal of disused structures
  • Removal of turnstiles and improvement to access points

The skatepark

The creation of the new 1,100m2 skatepark which opened in March 2018 saw the triumphant return of skateboarding to Crystal Palace Park, one of its historic homes given it was here in the park that the first UK national skateboarding competition took place in 1977.

The skatepark is the product of intensive collaboration between skatepark firm Canvas, Kinnear Landscape Architects, local riders and the Friends of Crystal Palace Skatepark. The design blends a highly contemporary approach while referencing the historic context of the park.

The skatepark is open during daylight hours, and to all users.

The cafe

The new Crystal Palace Park café opened to the public in May 2019. It was designed by Chris Dyson Architects using half round cedar shingles that imitate the scales of the nearby dinosaurs.

The ground floor is a dedicated café space, and the first floor is a event space available for private hire. Community use is at the heart of cafe's business model so corporate hire is limited to a maximum of 50 per cent of usage.

Dinosaur jaw surgery

In October 2020, the Grade 1 Megalosaurus experienced extensive damage to its head, particularly to large parts of the upper and lower jaw, following unauthorised access to the dinosaur island during the COVID-19 lockdown period. As a result, Bromley Council worked with partners Historic England and the Friends of the Crystal Palace Dinosaurs, to secure funding to undertake the necessary repair work to the jaw of the famous Megalosaurus in Crystal Palace Park. The works, which included the installation of a replica prosthetic jaw, were completed in May 2021.

This impressive sculpture was the first ever life-size reconstruction in 1854 of the first dinosaur recognised to science, making it the star of the internationally beloved, Grade 1 listed historic site.

The prosthesis was fabricated primarily from plastic, using white light scanning and 3D printing processes to recreate the fragmented section of the jaw. The 12 kg prosthesis has been attached to the head of the Megalosaurus, using interior metal hangers and iron rods, which have added stability to the body. The replacement sections have been painted to match the original features of the sculpture.

Posted
Download:

Image credit: Ruth Houlsby